Update - July 26th 2021

Screenshot 2021-07-26 at 14.38.18.png

Welcome to our weekly updates, we have decided to publish them on Mondays going forward to give a round up of the week before and keep everyone in the loop with what is going on.

4a51c5f0-a5a7-45d8-bfd2-97d880d655f1.JPG

We are thrilled to have managed to get concrete on site to pour the first two buildings as due to the worldwide effects of the pandemic concrete has been in short supply on island so we are grateful to our suppliers for putting us to the top of their list.

What you can’t see (or can see but might not realise at this moment) is the electrical and plumbing pipes that have done into the slab to be secured and hidden away ready for connection when the walls go up. Getting all of this preliminary work precisely correct is critical to the projects ability to stay on schedule which is why we take painstaking amounts of time and revision to the drawings before we bring the properties to market to ensure that they are built with function and with the end user always in mind.

We have also made great headway with the infrastructure for the project, having completed the drainage wells, and approximately 50% of the underground pipework for the electrical, gas and plumbing. Our transformer vaults have been positioned, that ensures that all the electrical supply lines for the project are safely underground and there are no overhead wires.

Our site sales office is fixed up and ready to welcome all purchasers to come and make their upgrade and standard selections when our interior design team has finalised their procurement.

Screenshot 2021-07-26 at 14.38.42.png

If you have any questions or would like any more information then please just email us & don’t forget to follow us on social media for to-the-minute updates whenever our sales team is on site!